Date Data Validation

Question:     I would like to ensure that the end date is greater than the start date?  Can this be done in MS Excel?

Answer:        Using Data Validation

Why:          When entering project tasks the end date has to be greater than the start date

Applies To: Excel 2003, 2007, 2010

 1. Refer to the data given below

 

 

 

 

 

2. Select the range; C2:C8

3. From the Data tab, in the Data Tools group, select Data Validation

4. Select as below;

 

 

 

 

 

 

 

 

5.         Select the OK button

6.         Enter 01/01/2011 in cell C2.An error message given below will be displayed since 01/01/2011 is less than 14/01/2011

 

 

 

 

 

 

Thus one is able to ensure that the data that users enter into a worksheet conforms to certain standards by enforcing the data validation rule